Friday, October 1, 2010

When it rains, it pours

With the massive amount of rain this, the entire lot turned into a muddy mess.  Good timing for the electrical service inspection, plumber to start, stone to be delivered, siding to be delivered, mason to finally show up, garage doors to be installed, well to be connected, etc.  No workers on site at all last week.  This week was crazy.  When it rains, it pours...
200A electrical service trench with conduits for electric, telephone, and cable.   You can see the fully shingled roof too!
Service entrance.  No meter yet (waiting for national grid): one week and counting

Garage doors are in.
Mason finished the stone veneer behind the wood stove today.
Plumbers roughed in the drain lines earlier this week.  Couldn't get up the driveway to do water lines today due to massive amount of mud.
Speaking of "mud," this thing better work...
I successfully wired one bedroom then Steve gave me some tips.  Did one more tonight.  Lots more to go.
This gives the "water service trench" new meaning.  Hopefully I can drain and prep it by Monday so they can hook up the well.  It takes A LOT of water to fill a 4' deep by 100' long trench.

1 comment: